bit more progress
Installed and resoldered the switch loom.
Installed and resoldered the lamp loom.
Installed coil loom (waiting for few mechs to come back from zinc plater before i can install them) still need to wire up flasher sockets
So the back is pretty much done apart from the few mechs but shouldn't take long to build / install (flippers,fault line,VUK,drop targets)
Started to populate the top a bit with any components that did not require drilling. Will now need to open up the pilots holes and drill some larger post holes to fit other stuff.
made a few mistakes
some how missed a t-nut and put a 6-32 where a 8-32 should be but luckily they are quite near the edge so using a large g-clamp should be able to press fit them in (as can't hammer now) biggest mistake is i did not realise the pop bumper mech screws are flush with the pf and you need to counter sink those holes before installing those 3 fin screws. It does not seem to effect the pop operation at all but is not cosmetically right so a bit annoying. As they are now all wired up and cant really lay pf flat any more id do more damage trying to remove and redo it. So will leave it.
One question! all the new standup targets slightly lean inwards is this correct? or should they be perfectly straight up ie 90degrees from pf?
Really need to start the wood work which i have been putting off as have zero experience with wood/sanding/filler/painting so will be quite hard for me and plenty of mistakes no doubt! but gonna need a cab pretty soon to stick the pf in
Regards